Ledger

DateKindStageActorClaimValueConfidenceBears onSource
2026-09-24priceMemory and storage (HBM, DRAM, NAND)TrendForce4Q26 forecast: NAND Flash contract prices up 15% to 20% quarter on quarter, enterprise SSD up 23% to 28%15 % QoQreportedstack: memory/nand_contract_price_qoq_4q26_lowTrendForce, 4Q26 Memory Price Forecast, public summary (2026-09-24)
2026-09-16statementGrid, interconnection and transformersERCOTOf 9,456 MW of large load approved to energize, a non-simultaneous monthly peak of 4,316 MW was observed operating in August 20264,316 MWconfirmedstack: grid/ercot_large_load_observed_operating_gwERCOT Monthly Operational Overview, August 2026 (2026-09-16)
2026-09-01contractGPUs, servers, racks and networkingDell TechnologiesAI server orders of $60.9 billion in the quarter to July 31, 2026 against $16.4 billion shipped; AI server backlog of $95 billion, about 5.8 quarters of shipments at the current rate95 USD bnconfirmedstack: systems/dell_ai_server_backlogDell Technologies Q2 FY2027 earnings release (8-K exhibit 99.1, 2026-09-01)
2026-08-27statementData centre shell and coolingCBREUS primary colocation markets at mid-2026: a record 7,481 MW under construction, 80.4% of it preleased, and a record-low vacancy of 1.4%7,481 MWreportedstack: datacenter/us_primary_market_under_constructionCBRE, North America Data Center Trends H1 2026 (2026-08-27)
2026-08-25statementMemory and storage (HBM, DRAM, NAND)TrendForceDRAM and NAND expected to absorb 47% of major cloud providers' capital expenditure in 2026 and 68% in 2027 at current prices47 % of CSP capexreportedstack: memory/dram_nand_share_of_csp_capex_2026TrendForce press release (2026-08-25)
2026-08-11contractGPU-hoursCoreWeaveMore than $25 billion of net new customer commitments added in early Q3 2026, on top of the $104 billion backlog at June 3025 USD bnconfirmedCRWV: mw_contracted_per_quarterCoreWeave Q2 2026 earnings release (8-K exhibit 99.1, 2026-08-11)
2026-08-11buildoutData centre shell and coolingCoreWeaveActive power reached 1.5 GW and total contracted power about 3.7 GW at June 30, 2026; nearly 500 MW went live in the quarter1.5 GWconfirmedCRWV: mw_added_per_quarterCoreWeave Q2 2026 earnings release (8-K exhibit 99.1, 2026-08-11)
2026-08-05statementMemory and storage (HBM, DRAM, NAND)SandiskFiscal Q4 2026 revenue of $8.97 billion, up 51% quarter on quarter, about one-third from volume and two-thirds from price; fiscal 2026 revenue $20.25 billion, up 175%8.97 USD bnconfirmedstack: memory/sandisk_pricing_share_of_sequential_growth_fq4_2026Sandisk fiscal Q4 2026 earnings release (8-K exhibit 99.1, 2026-08-05)
2026-07-30contractGrid, interconnection and transformersAmerican Electric PowerSigned load agreements of 69 GW for load coming online by 2030 across its PJM, SPP and ERCOT utilities, 6 GW added in the quarter; the same figure was 24 GW a year earlier69 GWconfirmedstack: grid/aep_contracted_load_growth_through_2030American Electric Power Q2 2026 earnings release (8-K exhibit 99.1, 2026-07-30)
2026-07-29statementGrid, interconnection and transformersERCOTTracking approximately 474 GW of large loads seeking interconnection as of June 2026, about 90% data centres474 GWconfirmedstack: grid/ercot_large_load_requests_tracked_gwERCOT, Assessing the Grid, Texas Senate Panel 1 (2026-07-29)
2026-07-28buildoutMemory and storage (HBM, DRAM, NAND)SK hynix2026 capital expenditure guided to the high KRW 40 trillion range, against KRW 27.5 trillion in 202540 KRW trillionreportedstack: memory/sk_hynix_capex_2026_plan_floorSK hynix Q2 2026 earnings call, transcript (2026-07-28)
2026-07-22buildoutPower generation and fuelGE VernovaGas turbine equipment backlog of 53 GW plus 63 GW of slot reservations, 116 GW in all, against output of about 20 GW a year; at least 125 GW under contract expected by the end of 2026116 GWconfirmedstack: power/ge_vernova_gas_equipment_backlog_and_slot_reservationsGE Vernova Q2 2026 results (Form 8-K, 2026-07-22)
2026-07-03priceMemory and storage (HBM, DRAM, NAND)TrendForce3Q26 forecast: conventional DRAM contract prices up 13% to 18% quarter on quarter, NAND Flash up 10% to 15%13 % QoQreportedstack: memory/dram_contract_price_qoq_3q26_lowTrendForce press release (2026-07-03)
2026-06-01priceMemory and storage (HBM, DRAM, NAND)TrendForceConventional DRAM contract prices rose 93% to 98% quarter on quarter in 1Q26 and the DRAM industry's revenue rose 81%93 % QoQreportedstack: memory/dram_contract_price_qoq_1q26_lowTrendForce press release (2026-06-01)
2026-05-07statementData centre shell and coolingCoreWeaveChief executive: surpassed 1 GW of active power and on the way to more than 8 GW by 20308 GWconfirmedCRWV: mw_added_per_quarterCoreWeave Q1 2026 earnings release (8-K exhibit 99.1, 2026-05-07)
2026-04-24policyGrid, interconnection and transformersPublic Service Commission of WisconsinApproved We Energies' Very Large Customer and Bespoke Resources tariffs: a 15-year minimum term, a 100 MW threshold and full cost responsibility for dedicated generation100 MW thresholdreportedstack: grid/large_load_tariffsBizTimes Milwaukee (2026-04-24)
2026-04-09statementGrid, interconnection and transformersERCOTLarge-load interconnection requests of 75 MW and above reached 410 GW at March 26, 2026, about 87% of them data centres, up from 233 GW in December 2025410 GWconfirmedstack: grid/ercot_large_load_interconnection_requestsERCOT update to the Texas House Committee on State Affairs (2026-04-09)
2026-03-31financingGPU-hoursCoreWeaveDDTL 4.0 facility with $8.5 billion of borrowing capacity at SOFR plus 2.25%, non-recourse to the parent, entered March 20268.5 USD bnconfirmedCRWV: cost_of_debtCoreWeave 10-Q for the quarter ended June 30, 2026 (note 10)
2026-03-31statementGrid, interconnection and transformersGeorgia Power12,400 MW of large-load commitments across 31 customers, of which 8,500 MW had broken ground and ten projects were online12,400 MWconfirmedstack: grid/utility_large_load_commitmentsGeorgia Power, Q1 2026 Large Load Economic Development Report to the Georgia PSC (as of 2026-03-31)
2026-03-10policyPower generation and fuelMississippi Department of Environmental QualityAir permit issued for 41 permanent gas turbines, about 1.2 GW, at the Southaven site, where roughly 20 turbines were already running1.2 GWreportedstack: power/onsite_generation_permitsE&E News (2026-03-10)
2025-12-31priceMemory and storage (HBM, DRAM, NAND)SandiskSandisk shares closed 2025 at $237.38, 5.0 times the $47.15 close of February 18, 2025, its first week as a listed company, as NAND prices turned up5.03 xreportedstack: memory/sandisk_share_price_close_2025_endYahoo Finance, SNDK historical prices
2025-12-19policyPower generation and fuelGeorgia Public Service CommissionCertified about 9,885 MW of new Georgia Power generation to serve large-load growth9,885 MWreportedstack: power/utility_generation_certified_for_large_loadPerkins Coie summary of the PSC vote of 2025-12-19 (Dockets 56298 and 56310)
2025-12-17pricePower generation and fuelPJMThe 2027/28 capacity auction cleared at the $333.44 per MW-day price cap with 134,479 MW procured, 6,623 MW short of the reliability requirement; PJM attributes nearly 5,100 MW of the higher requirement to data centres333.44 USD/MW-dayconfirmedstack: power/pjm_capacity_price_2027_2028PJM Inside Lines (2025-12-17)
2025-12-17statementMemory and storage (HBM, DRAM, NAND)MicronPrice and volume agreements cover Micron's entire calendar 2026 HBM supply; fiscal 2026 capex plan raised to $20 billion100 % of 2026 HBM supplyreportedstack: memory/micron_hbm_calendar_2026_supply_contractedTrendForce News (2025-12-18) reporting Micron's fiscal Q1 2026 earnings call of 2025-12-17
2025-12-01buildoutPower generation and fuelEntergy LouisianaBroke ground on two combined-cycle units of about 1,500 MW at Richland Parish for the Hyperion campus, both expected operational by late 20281,500 MWconfirmedstack: power/dedicated_generation_for_campusesEntergy Louisiana newsroom (2025-12-01)
2025-09-08contractGPU-hoursNebiusFive-year agreement to supply Microsoft with dedicated GPU capacity in tranches from a new data centre in Vineland, New Jersey; total contract value about $17.4 billion through 2031, with options that would increase it17.4 USD bnconfirmedNBIS: revenue backlog (model pending)Nebius Form 6-K, 2025-09-08
2025-09-05priceMemory and storage (HBM, DRAM, NAND)SandiskSecond 2025 NAND price increase of 10% notified to customers, with the market expected to stay undersupplied through 202610 %reportedstack: memory/sandisk_price_increase_sep_2025TrendForce News (2025-09-17), citing TechPowerUp's report of the customer letter
2025-08-20policyPower generation and fuelLouisiana Public Service CommissionApproved, 4 to 1, a settlement letting Entergy Louisiana build three combined-cycle gas plants and new transmission for the Meta campus (Docket U-37425)3 plantsreportedstack: power/dedicated_generation_for_campusesKNOE (2025-08-20)
2025-03-31contractGPU-hoursCoreWeaveMaster services agreement under which OpenAI committed payments of up to approximately $11.9 billion11.9 USD bnconfirmedCRWV: revenue_backlog_usd_bnCoreWeave final prospectus (424B4, 2025-03-31), pp. 33 and 158
2025-03-07priceMemory and storage (HBM, DRAM, NAND)SandiskCustomer letter announcing NAND product price increases of more than 10% from April 1, 2025, citing tariffs, consumer inventory cuts and industry output cuts10 %reportedstack: memory/sandisk_price_increase_apr_2025Yahoo Finance / Investing.com (2025-03-07), reporting the customer letter
2025-02-19policyGrid, interconnection and transformersIndiana Utility Regulatory CommissionApproved the large-load tariff settlement in Cause No. 46097; the record names Amazon's New Carlisle campus as a 2,250 MW load, the largest customer in the utility's history2,250 MWconfirmedstack: grid/large_load_tariffsIndiana Utility Regulatory Commission, Order in Cause No. 46097 (2025-02-19)